1.Payment by Results The Incentive Scheme
as per the IR Code for Mechanical Department (Workshop): by Hemant Kumar, Sr.
Professor, IRIMEE, Jamalpur
This paper presented the provisions of the incentive scheme as laid down in the Indian
Railway Code for Mechanical Department (Workshop), based on chapter 4. It also contained
the forms and formats as per chapter 5 of the code.
The points of discussion that followed were:
- Many workshops are following the timings circulated by CLW way back in early 1960s.
Since the facilities may vary, blindly adopting the timings of CLW is not correct.
- Code is clear as to where synthetic times could be used (manipulation values, setting-up
values, loading/unloading values, tool-changing values and preparational values)
- Synthetic times should be based on average of observed times of the past,
implying actual time-study.
- Synthetic time should not be confused with computed time, which depends on
the metal removal required and the rate at which it can be performed on the machine used.
- Block Time: The code does not mention about block-time. However,
block-time based on observed average of activities like POH, repairs, etc. can possibly be
used. Ad-hoc time based on judgement may not be appropriate.
- Idle-time: Para 424 provides for fixing a minimum machine break-down
resulting in booking of idle-time
which, when exceeded, should result in NIL
incentive bonus to the maintenance gangs. However, no guidelines are available in the code
as to what this percentage should be.
- Allowed time for similar activities across the workshops: The participants
felt that there should be a standard allowed time for common activities that are performed
by many workshops. This could act as a guideline, but some variation due to local
conditions may be permitted within a short band. The ideal conditions for the ideal time
may also be laid down for ascertaining if any variation may be allowed or not.
2. Auditing of Incentive Scheme A study Report:by
P. K. Mishra, Dy. CME, ER, Jamalpur
The paper shared the experiences in checking the malpractice in incentive scheme
implementation in Jamalpur Workshop. The shortcomings noticed and remedial actions taken
are given below:
- Plus cards or Excess-Time cards:
- Plus cards issued on flimsy grounds, and not investigated.
- Now only PE approves. No Excess-time cards issued in 2-1/2 years
- Loss cards destroyed; out-turn taken in subsequent month, raising profit.
- Now only current cards are accepted.
- All cards punched off during the month are sent to accounts office for accountal and
payment.
- Missing hours have been minimised as a result of the above actions.
- Idle-time cards were put up to AWM at the end of the month, not as and when arising.
- Idle-time cards were not having signatures of time-booth clerk.
- No record in the section was there on a daily basis
- Now record in the section is being kept for idle-cards daily, indicating time IN and
time OUT, reason, description of job, etc.
- AWMs are now signing the Idle-time cards as and when they arise.
- Many workers were observed to be idling frequently, at the same time adequate incentive
profit earned, indicating slack in the Allowed Time.
- In 2-1/2 years 68 items have been studied and ATs revised. 115 627 man-hours saved per
month, i.e. requirement of 500 DWs reduced for doing the same work.
- Disproportionate booking of EIW:
- Due to change/ reduction of the workload, less DWs were booked than the sanction, but
corresponding reduction in EIWs not there.
- Machinists available were more than the machine-shifts available, and the surplus men
booked as EIW.
- Now EIWs booking are made as per the original/ laid down ratio of DWs
- Surplus machinists have been trained in fitting job, and utilised in the sections where
work was there.
- EIW booking reduced from 1929 two years back to 1363 now. Further reduction of 443 is on
the anvil due to the new timings.
- Cards punched in a month were not being deposited 100%. Some retained for future.
- Piecework number was being given serial number every month. This was resulting in all
losses being booked against the last few cards every month, and destroyed or retained.
Casual check would indicate continuity, which will be misleading.
- Now cards are checked for continuity of piecework number, and all previous and current
numbers accounted for.
- Numbering system has been changed to Annual system. The loss-cards cannot be hidden from
month to month.
- Same out-turn reckoned by different sections:
- Credit of out-turn was taken by different sections for the same product, or by the same
section more than once, as there was no cross-checking.
- Now material actually received in stores is taken as the physical out-turn of the shop
and the incentive out-turn is synchronised with the physical out-turn.
- Ineffective time-booth staff:
- Job cards were not kept in the custody of the time booth clerk but left with the
section-chargemen or even with the artisan staff.
- Time booth clerks were not posting tally-sheets on a daily basis with the help of GA
cards, Job cards, etc.
- Counselling of time-booth clerks and surprise checks on the booths by the officers
concerned have been started.
- Non-Stock Requisition (NSR) and Shop-on-shop (SOS) work-orders:
- NSR and SOS work-orders were placed with inflated requirement. While production was as
per actual requirement, out-turn was claimed as per the work-order quantities.
- Several fictitious SOS work-orders were placed by shops for the repairs to be done by
itself.
- Now NSR and SOS work-orders cannot be placed without the approval of the AIO or the PE.
- For easy monitoring, assisting shops have been given block-timings.
3. Sensitivity Analysis of Incentive Scheme: by Subrato
Nath, Dy. CME, ER, Jamalpur
This paper presented a mathematical model showing the sensitivity of shops for
manipulation, by managing sectional imbalances. It made the following assumptions for the
modelling:
- A shop has four sections A, B, C and D
- Gate Attendance Hours (GAC) remain constant.
- Out-turn in physical terms remains the same.
- Allowed time is reduced by 12% and Incentive rate is increased by 4 times.
The presentation showed that by manipulating the section out-turn of one section to
report loss, the shop can gain tremendously overall. The gain was shown to be up to > 8
times the earlier incentive payment if the shop was earning about 15% incentive earlier,
but it was only about 2.75 times if the shop was near 50% of incentive earning earlier.
The author suggests the following checks to control this manipulation:
- Check the increase in incentive earnings and drop in incentive percentage
- Use the table to calculate ideal earning
- Check out if cyclic variation of gain/loss in incentive is there
- Check for sudden loss in certain sections
- Reduce the number of sections doing the same job within the same shop
- Fix sectional targets for such sections
- Tighten the Inspection staff
4. Management Response to Incentive Scheme: by Ashutosh
Swami, Exec. Dir./ Workshop/ Railway Board
After briefly telling about why we should be having an Incentive Scheme at all, the
author mentions that the function of PCO in Workshop for incentive is similar to control
room in Divisions for running the trains. In his view, the present problems are due to:
- Gradual erosion in working and effectiveness of PCO which in turn has affected the
performance of incentive system.
- Compilation of vital incentive performance data not done completely. Data are not
analysed at any level.
- PEs have been given all kinds of sundry jobs such as rolling stock movement inside the
workshop.
- Staff inducted in PCO without formal training. No refresher course for updating the
knowledge and proficiency.
- Supervisory staff not fully involved in the working of incentive system. Their interest
limited to ensuring certain percentage of incentive earning only.
The author suggests that the following action may be taken to improve things:
- Involve Sectional supervisor to monitor parameters such as actual output in man-hours
and units against planned, load lifted per DW
- Actual booking of staff (DW, EIW) against sanctioned strength. Less booking of staff
should be rare and done only on justified grounds, and that too with the approval of PE
& Dy.CME.
- Reasons for high absenteeism of DW and EIW, particularly the ones who are habitual to be
investigated and corrective measures taken. Absenteeism will come down if supervisors are
asked to book all the DWs, as the section % is dependent on the number of DWs in the
section.
- REVITALISED PCO FUNCTIONING
- Keep Master Planning card for all repair and manufacturing activities.
- Only printed job cards and computation-cum inspection sheets for squad working with
proper serial no. to be used.
- Serial no. of all job cards accounted for payment in a month should tally with the
serial no. given by time keeper office.
- Correlation between % incentive earning and amount of incentive paid.
- Section and shop-wise details of actual output in units and man-hours vis-à-vis planned
workload. Analyse the reasons for shortfall.
- Details of section/shop where booking of staff is less than the sanctioned strength.
Analyse reasons for such booking.
- PRO-ACTIVE FUNCTIONING OF PE
- PE should exclusively look after PCO jobs only.
- PE should monitor and analyse the following incentive performance parameters and
initiate corrective action:
- Load lifted per direct worker (actual Vs. planned).
- Utilisation of machines (actual Vs. planned).
- Trend of AT per unit of equated out-turn for POH out-turn and out-turn of spares such as
wheels, springs, brake block etc.
- Trend of shop and section-wise percentage incentive earning. Monthly fluctuation in
earning from shop to shop and also sections of the same shop. If so, reasons thereof and
corrective action taken.
- Analyse section/shop-wise absenteeism. Specifically where absenteeism is more than LR
and unauthorised absenteeism is more than 2%.
- Analyse shop-wise and section-wise details of following exception statements:
- Extra Time or Plus Time Card (No. & quantum in man-hours).
- AT accounted for Material Scrap.
- Entire working of incentive scheme including generation of managerial information
statement should be computerised.
- This will also facilitate quick detection of irregularities and timely corrective
action.
- Computerise the Gate Attendance Recording System.
- Staff inducted in PCO organisation should be given mandatory training on incentive
working.
- Refresher course should also be organised at regular intervals for staff, supervisors
and officers looking after the incentive functions.
- PEs Conference should be organised at least once a year to share ideas, exchange
data and other inputs useful for standardisation of norms.
5. Revision of Incentive Scheme
in Liluah Workshop:by P. K. Saha, Dy.CME/ ER/ Liluah
The single most important effect of the new orders in Liluah Workshop has been complete
elimination of incentive overtime. The various shortcomings noticed were as follows:
- Inoperative time recorder clocks.
- Non submission of completed job cards to the accounts department within 48 hours of
completion of job cards.
- Submission of job cards in lots rather than in piecemeal manner.
- Rate fixers not carrying out intensive checks on shop floor to detect irregularities.
Rate fixers not investigating the cases of abnormal profit or losses.
- Inspector not insisting on all production documents prior to certifying the completion
of job.
- Tendency not to utilise the full strength of workers on incentive.
The author also pointed out to the anomaly in the Railway Boards Letter No.
PC-V/98/1/7/4/1 dated 21.6.99, in that 12% saving in AT is not possible even with
zero contingencies, in case the AT already had only 12.5% Fatigue Allowance.
He also expressed the fear that in absence of adequate additional load the new
capacity generated will remain under utilised.
6. Malpractices Noticed in South
Central Railway Workshops: by S. Vasudevaiah, PE/ SCR/ Lalaguda
The author enumerated the malpractices noticed in the implementation of Incentive
Scheme, and the corrective action taken on S. C. Railway as follows:
- Process improvements not reflected in the job/ route-cards: The route
being followed on the shop floor was different from the indicated one. The improvement in
the process was not reflected in the master route-card.
- A check on the processes being followed resulted in downward revision of AT, and change
incorporated in the master card. Raw material was also changed. The process-checks are
continuing at LGDS.
- Additional and unnecessary operations included in the job: It was found
that the die made for a forging item had excess machining allowance, and the shape
provided for additional machining operation.
- Cross-checking with the machine shop resulted in the die getting modified, reducing the
AT for machining operation.
- Skipping some operations on store-work-orders as well as repair work-orders: Operations
indicated in the route-card were not being carried out fully, and inspection wing was
colluding in passing the same and sending to the Stores. On repair orders, the actual
repairs done were not as per the card. Full work required for heavy work was
not done and some operations were being skipped. Credit was being taken for the full
scheduled work.
- Tightening the Inspection and taking up with the people involved has improved the
matters.
- Discrepancies in issuing job-cards:
- It was noticed that the job-cards issued for some work were being used for some other
work by making corrections in the descriptions/ AT, etc. by ink, without even the
rate-fixers sign let alone being authorised by the PE.
- In some job-cards, multiple operations had been printed and the rate-fixers strike out
those not applicable.
- Hand-written corrections are now not being allowed, and the job-cards with
multiple choice have been corrected.
- Abnormal profits: The code stipulates that abnormal profits should be investigated.
While the statement of excess-earnings was being sent by accounts no action was being
taken by planning department.
- Investigations have been started in cases of Excess-earnings.
7. Revision of AT and
Incentive Bonus Rate in Railway Workshops Pitfalls and Suggestions: by R.
Nagarajan, PE/ SR/ Golden Rock
The author introduced the concept of total cost instead of only incentive
bonus payment. He showed that the increase in unit labour-cost for the same percentage of
incentive earning before and after the revision of rates would be hardly 4-5% at 50%
incentive level, because the total production also increases.
The pitfalls were nearly the same as those mentioned by PE/ LGDS, though with different
examples.
His suggestions were:
- Neutral CWSs may be asked to advise coach-wise rejections in writing. Presently they
point out but the shops themselves note down the defects.
- 15% payment to SSEs should be linked to
- Incentive earning of the shop
- Industrial safety record
- Cost-reduction measures taken
- No. of days of attendance
- Impart training to Union-leaders in their role/ responsibilities.
- Multi-skilling at least from the next recruitment.
- Workshop modernisation/ expansion to synchronise with manpower planning.
8. Functioning of Incentive Scheme in Kharagpur Workshop
After September 1999: by Manish Kumar Gupta, PE/ SER/ Kharagpur
The main thrust of this presentation was the fact that in Kharagpur workshop, the
documents pertaining to the incentive scheme have been computerised, and instead of Bradma
printing, computer printing has been started. This has made possible the posting of
out-turn in the Inspection sheets also through computer. Plans are afoot to extend the LAN
to the shops so that challan, progress of work-order, gate-pass, etc. can be done through
computers only.
He mentioned that in the Electrical shops the PCO was earlier not being allowed to
function and no inspections, no time-studies were done. After Sept. 1999, it has been
brought under PE; redundant activities have been deleted and time-study undertaken.
He mentioned that Kharagpur Workshop has started action on the concept of inter-shop
tenders for the works that do not require special training/ skill. This would
reduce the mismatch in the availability of workers.
He also feared that there might not be sufficient load for the entire workshop
for people to be able to earn reasonable incentive.
9. Implementation of Revised ATs in Matunga Workshop:
by J. P. Vyas, PE/ CR/ Matunga
The salient point brought out in the presentation was that with the implementation of
the revised Allowed Times, the incidence of Incentive-Overtime has been totally stopped.
His suggestions were:
- Incentive sanction may be based on 3 months basis instead of three years at present
- Some external agency may carry out fresh work-study.
- With the 15% allowance to SSEs, there may be no SSEs willing to join group B services.
Also with the discrepancy in the allowance between the shop SSEs and the PCO SSEs people
would not come forward to join PCOs. This order, therefore, needs to be reviewed.
10. Incentive
Western Railway Experience: by Ashutosh Gangal, DyCME/ WR/ Lower Parel
The paper mentioned many malpractices, many of which were brought out earlier by other
participants. Some of the notable ones are reproduced below:
- Ad-hoc block timings have become common, inflating allowed time.
- Absence of any reliable benchmarks for comparison across workshops - inflated timings
have become quite common in all workshops
- Time-studies have proved amenable to misuse and resulted in inflated timings
- No direct relationship of incentive with the physical out turn of coaches / wagons
- Gangs earn and lose incentive in a cycle.
- Transfer of work from one gang to another to optimise gain.
- No volunteers for PCOs due to lower wages result in posting of junior most staff.
- Lack of load for all the workers
The author gave some suggestions as well:
- Permission for block timing should become more restrictive
- Benchmarking of timings for comparison across workshops - implement low times for
each activity in all shops.
- Use of work sampling, synthetic timings & PMTS for calculating allowed times
- Treating plus times at par with idle time.
- Even if booked, the idle time should not be accounted for in incentive calculations
- Changes of machinery to compulsorily reflect in reduction in allowed timings
- Direct relationship of incentive with the physical out turn needs to be created
- Time lost should be carried forward for incentive calculations. This will
prevent cyclical loss/ profit situations.
- Gang incentive or individual incentive earning should be multiplied with capacity
utilisation factor to link incentive with physical output.
- Salary differential between PCO & shop floor should be narrowed down
- System of compulsory Cadre-review in workshops needs to be introduced.
- Annual review of shop manufactured items for economic-viability.
11. Implementation of new orders in ICF: by R. Ganesan,
PE/ ICF
The focus of the presentation was on the implementation of the revised timings, and the
teething troubles faced by ICF. The gain from implementation of the new orders was
complete stoppage of over-time for incentive staff. One of the malpractices noticed was:
- Proceeding Time cards: The proceeding time cards were being manipulated, and were not
linked properly later on.
- Now the life of PT cards has been fixed at a maximum of three months, after which they
are converted into missing hours.
12. Implementation of revised orders in Gorakhpur
Workshop: by R K. Arora, PE/ NER/ Gorakhpur
The points brought out by the author were already covered in the other papers. The
experience of Gorakhpur workshop was similar to others.
13. CLW Incentive Scheme vs. Other Incentive Schemes:
by S. Chak, CME/ ICF
The author compared the CLW pattern of Incentive Scheme with the other schemes
prevalent in the world. Then he mentioned about the data that should be monitored by the
executive. The data included the following:
- Manpower utilisation
- Absenteeism
- Average Load lifted per DW
- No. of employees paid incentive bonus and average incentive paid
- Sections earning > 45% incentive.
He then discussed about some important points in regard to the incentive scheme
implementation:
- The standard-hours calculations mention a factor of 208. This is based on 48-hour week.
Even though some workshops may be working only 45 hours a week, yet they have to
take 208 as the figure (as if they were working for 48 hours a week)
- The incentive staff calculations must be on the basis of 48-hour week.
- Leave reserve is only for Direct workers, and not for EIW.
- The sanctioned strength of EIWs and IWs must not be exceeded. If there are more people
(surplus staff), they must be booked as DWs only.